Residual Budget Deviation (Inverter)

Residual Budget Deviation is the difference between the default energy budget and the sum of Energy Actual and all known deviations to the forecasted budget (including the Weather Adjustment).

This signal can consist of both a positive part of uncategorized loss deviations, as well as a negative part of loss deviation that is covered by more than one category.

Residual Budget Deviation = Default Energy Budget - ( Energy Actual + Weather Adjustment + Performance Ratio Budget Deviation )

Notice

This is a helper signal, which means it is used to calculate other signals, but is not available in the signal selector.

Technology

Solar: Inverter

Equation
residual_budget_deviation_inverter_eq.jpg

where:

ΔLPbudget,dev

is the Residual Budget Deviation

Ebudget

is Energy Budget - Default

Eactual

is the exported energy

Adjweather

is the Weather Adjustment

ΔLPbudget,pr

is the Performance Ratio Budget Deviation

Inputs