Lost Production to Downtime and Curtailment Total

Lost production to downtime and curtailment total takes the highest value between lost production to curtailment total and lost production to downtime, for 10 minutes intervals, as reference. This variable indicates all the losses caused by curtailment and downtime. It is important to note that this variable does not correspond to the sum of lost production to downtime and curtailment total, as it always takes the maximum of both variables.

Technology

Wind

Remarks

Normally, only one of Lost Production to Downtime or Lost Production to Curtailment (Total) is defined and not both.

Equation
Lost_Production_to_Downtime_and_Curtailment_Total_-_Equation.png

Where:

ELPtot

is Lost production total

ELPC

is Total Lost Production to Curtailment

ELPD

is Lost Production to Downtime (Turbine)

Inputs
Lost_Production_to_Downtime_and_Curtailment_Total_-_Inputs.png
Usage Example

This section will be updated later.