Lost Production Contractual Inverter

This is a lost production signal that accrues lost production during stop events categorized as unavailable. If a stop event occurs with a category that should be available, then no lost production will be accrued.

Technology

Solar

Remarks

N/A

Equation
Lost_Production_Contractual_Inverter_-_Equation.png

Where:

ELP,contract

is the Lost production contractual

Epotential+

is the potential energy production, clamped to the positive part

Eactual+

is the Energy or Power with Fallback, clamped to the positive part

ATC

is the Time-based Contractual Availability (Inverter), ATC in [0..1]

Pcp,contract

is Cascading Potential Power - Solar

T

is the device resolution in hours

Inputs
Lost_Production_Contractual_Inverter_-_Inputs.png
Usage Example

The following example shows a correlation between a dip in time-based contractual availability and lost production (contractual):